The arc at a glance
Fire restoration runs through six stages in order, and each one has a typical duration in the Puget Sound market. These are realistic ranges, not promises; your house, your carrier and your jurisdiction set the actual dates.
- Secure and assess: day 1 to day 2.
- Mitigate and clean: week 1 to week 4.
- Scope approved by the insurer: week 2 to week 6.
- Permits and engineering: week 3 to week 8.
- Rebuild: month 2 to month 6 or more.
- Close out: final inspection, punch list, last payment.
A smoke-only loss stops after stage 2 plus a short rebuild of whatever burned, which is why it is measured in weeks. A structural fire runs all six, which is why it is measured in months.
Stage 1: secure and assess (days 1 to 2)
The fire department releases the house. The same day, the restoration crew boards up openings, tarps the roof, sets HEPA air scrubbers and, if water was used, starts extraction and drying. Within 48 hours the crew has photographed every room, mapped where smoke and water went, inventoried what is obviously non-salvageable and written the emergency invoice that goes to your carrier. Emergency board-up and assessment and estimates describe this stage.
What you do: report the claim, get the claim number and adjuster, start the receipts folder, decide where you are sleeping. Do not clean, do not throw anything away, and do not run the furnace.
Stage 2: mitigate and clean (weeks 1 to 4)
Soot and smoke residue are removed room by room, top down. Contents are sorted, cleaned on site or packed out, and inventoried. Wet materials that will not dry are removed. The HVAC is cleaned or its ductwork replaced. Odor treatment happens last, with the house empty, followed by sealing of framing and subfloor that cannot be fully cleaned.
A kitchen fire with main-floor smoke takes one to two weeks here. Whole-house smoke, or a fire that reached two or three rooms, takes three to four. Demolition of charred structure happens in this stage too, down to clean framing, so the rebuild starts from a known condition. Smoke and soot cleanup and odor removal and sealing cover the methods.
Stage 3: the insurer approves the scope (weeks 2 to 6)
This stage decides the schedule more than any other. The contractor writes the rebuild estimate in Xactimate, the line-item format your carrier uses. The adjuster inspects, compares, asks questions and approves a scope. Items the adjuster missed or that are discovered during demolition become supplements, each of which goes through the same review.
Where time is lost: incomplete first estimates that trigger rounds of supplements; adjuster workload after a regional event; disputes over whether something is cleaned or replaced; and homeowners who have not yet chosen finishes, which stalls the estimate's allowances. A thorough assessment in stage 1 and one contractor for the whole job shorten this stage considerably. The working with your adjuster on the rebuild guide explains how to keep it moving, and repair or rebuild covers the decision when damage is extensive.
Stage 4: permits and engineering (weeks 3 to 8)
Any structural repair needs a building permit, and in King, Snohomish, Pierce and Kitsap counties and their cities that means plans. Charred rafters, joists or bearing walls need a structural engineer's letter or drawings. Electrical, plumbing and mechanical work that is replaced gets its own permits. Submittal to issuance runs from a few days for a simple repair to several weeks for engineered structural work, longer in the busiest jurisdictions.
This stage overlaps with stage 3 when it is done right: the contractor submits as soon as the structural scope is known rather than waiting for the carrier's final approval of finishes. Long-lead materials, windows, cabinets, specialty flooring, trusses, are ordered the day the scope is approved, because their lead times are often longer than the permit.
Stage 5: rebuild (month 2 to month 6 or more)
Framing, roofing and exterior envelope first; then rough electrical, plumbing and mechanical; insulation; drywall; finishes; cabinets, fixtures and flooring; paint; and the exterior. Each rough-in has an inspection before it can be covered, which is why the stages cannot be compressed by adding people.
Typical durations once permits are in hand: a kitchen rebuild after a contained fire, three to six weeks. A room or two rebuilt to the studs, two to three months. A roof and upper floor, four to eight months. Full gut and rebuild, eight months to a year, with the structural work and material lead times setting the pace. Fire damage repair and reconstruction describes what the rebuild includes, and kitchen fire restoration the most common case.
Stage 6: close out
Final inspection and certificate of occupancy where required, the punch list walk with you, the final invoice to the carrier for the approved scope and any approved supplements, depreciation released on replacement-cost items once the work is complete, and your deductible, which is applied exactly as your policy states.
Where weeks go missing, and how to keep them
- An incomplete first estimate. Every supplement is another review cycle. A thorough stage-1 assessment is the best schedule tool there is.
- Two contractors. A mitigation company and a separate builder leave a gap where nobody owns the schedule. One contractor from board-up to paint closes it.
- Late permit submittal. Submit structural scope early; finishes can follow.
- Undecided finishes. Pick cabinets, flooring and fixtures while the scope is in review, not after permits issue.
- Material lead times. Order long-lead items the day the scope is approved.
- Waiting to call. Soot etches and water grows mold from day one; the clock on stage 2 starts whether or not a crew is there.
If you are at the beginning of this, the next step is one call: (844) 543-5757. Dispatch routes a Washington-registered fire restoration contractor across King, Snohomish, Pierce and Kitsap counties who handles board-up, cleanup and the structural rebuild under the scope your adjuster approves, on one schedule and one claim file.